Issues delaying the delivery schedule of the Casoni improvised landing strip

isrlaspezia_AMb4f1_299.jpg

Title

Issues delaying the delivery schedule of the Casoni improvised landing strip

Description

Reports on delays to the construction of the Casoni improvised landing strip: the specialist showed up only on the first day, never to be seen again and work is hampered by mud. Asks permission to suspend the works next Sunday and Monday, being festival days.

Publisher

IBCC Digital Archive

Date

1945-03-28

Rights

This content is property of the Istituto spezzino per la Storia della Resistenza e dell’Età Contemporanea which has kindly granted the International Bomber Command Centre Digital Archive a royalty-free permission to publish it. It has been published here ‘as is’ and may contain inaccuracies or culturally inappropriate references that do not necessarily reflect the official policy or position of the University of Lincoln or the International Bomber Command Centre.

Format

One-page typewritten note

Language

Identifier

isrlaspezia AMb4f1 299

Spatial Coverage

Temporal Coverage

Collection

Tags

Citation

Italy. Comitato di Liberazione Nazionale. Colonna ‘Giustizia e Libertà’ and Scaramuccia, “Issues delaying the delivery schedule of the Casoni improvised landing strip,” IBCC Digital Archive, accessed December 12, 2019, https://ibccdigitalarchive.lincoln.ac.uk/omeka/collections/document/11876.

Item Relations

This item has no relations.

Can you help improve this description?